Three Liebherr Cranes from Affolter Transporte AG Build Wildlife Bridge at Night in Switzerland

Three Liebherr Cranes from Affolter Transporte AG Build Wildlife Bridge at Night in Switzerland

Several wildlife crossings are currently being constructed across motorways in Switzerland. At one such new wildlife bridge on the A1 motorway near Solothurn, the Bern-based company Affolter Transporte AG recently installed massive timber beams. Due to the required temporary closure of the motorway, the operation had to be meticulously planned and executed. Over six perfectly coordinated night shifts, the 38m long elements were installed on schedule.

During the construction of a major wildlife crossing, crane and transport company Affolter from Schüpfen (Canton of Bern) installed the substructure of the new bridge over six nights. The key challenge in this project was the narrow time window for motorway closures, between 23.00 and 05.00.

 

100 percent Liebherr: Working in tandem with a new EC-B tower crane, two LTM mobile cranes handle the demanding nighttime operations.

 

Each night, up to 10 timber beams, each 3m high and 38m long, had to be delivered and lifted into place. Among the equipment on the A1 motorway was the Liebherr LTM 1300-6.2 – the most powerful crane in the family-run company’s fleet. With a maximum radius of 25m, the six-axle crane placed its 20 loads at half-hour intervals. The slightly curved timber beams span all four lanes of the motorway without intermediate supports.

 

At dusk: The first components are loaded onto the heavy transporters at the storage site. A 20-year-old LTM 1100-5.1 takes
care of this task

 

The long timber elements were delivered from Rapperswil, around 20 kilometres away. A 20-year-old Liebherr mobile crane loaded them onto the trailers of the heavy transport vehicles at a storage site. Upon arrival at the construction site, an LTM 1160-5.2 unloaded the cargo and placed the beams into a holding frame. The larger mobile crane then hooked the bulky loads and installed the beams.

 

Also on site: An LTM 1160-5.2 was positioned on the closed carriageway to unload, upright, and place the timber beams into a
holding frame for the 300-tonne crane.

 

The night operations ran like Swiss clockwork, ensuring the carriageways were cleared by early morning and reopened in time for rush-hour traffic. In addition to the three Liebherr cranes, Affolter deployed four tractor units and two escort vehicles each night. After just under a week, the timber structure of the bridge was completed. The finished wildlife bridge will span more than 50m in width.

 

Crane operator Mathias Alram picks up the 3-metre-high components with his LTM 1300-6.2 and…

 

The company, led by brothers Ernst and Rudolf Affolter, employs 45 staff across four locations in the cantons of Bern and Aargau. In addition to a city crane, the extensive fleet includes five Liebherr mobile cranes and five mobile construction cranes for lifting operations, including two Liebherr MK 88-4.1 models. In the company’s other divisions – transport, industrial relocations, and storage – numerous escort vehicles, truck-mounted cranes, mini crawler cranes, aerial work platforms, forklifts, and various special trailers are in use.

 

…delivers them for installation.

 

Featured Title photograph

Spanning the motorway: The 38-metre-long timber beams bridge the entire motorway without intermediate supports. A Liebherr
EC-B top-slewing crane installs the cover plates onto the beams.

 

Source     

Het bericht Three Liebherr Cranes from Affolter Transporte AG Build Wildlife Bridge at Night in Switzerland verscheen eerst op Heavy Lift News.